SREDA | National Database of Renewable Energy

Project/System ID Number: 4206

Item Name Information
System Name : 10 kW Solar Net Metering System on Nurpur 33 by 11 kv Substation at SND2 Pabna
System ID : SID # 4206
Technology Type : Net Metering Rooftop Solar
Grid Status : On Grid
Capacity : 10 kW
Completion Date : 2021-07-29
Present Status : Completed & Running
System Owner : Northern Electricity Supply Company Limited (NESCO) (51)
EPC : Northern Electricity Supply Company Limited (NESCO) (51)
Financing Org. : Own Investment (Self)
Inserted by : Md. Yeaseer Arafat (216)
Creation Date : 2021-08-01 01:33:19
Updated by : -
Modification Date : -
Item Name Information
Implementing Agency : Northern Electric Supply Company Ltd. (NESCO)
Office/Program : -
PD Name : Executive Engineer, Planning, NESCO
Division : Rajshahi
District : Pabna
Upazilla : Pabna Sadar Upazila
Location : Nurpur
Latitude, Longitude : 24.024484, 89.234597
Note : Nurpur 33 by 11 KV Substation
Expected Energy Generation and CO2 Emission reduction during System Life : 218 MWh, 103 tCO2
Expected Energy Generation and CO2 Emission reduction till today : 2 MWh, 924 kgCO2
 
Report on the System/Project